Maryland SWPPP Compliance

Quick Facts for Maryland

  • Authority: Maryland Dept. of the Environment (MDE) (MD)
  • Permit: General Permit for Construction (20-CP)
  • Inspection Schedule: Every 4 business days OR weekly + post-rain
  • Rain Trigger: 0.25 inches or more in 24h
This page is a field reference, not legal advice. Confirm the current permit, local requirements, and project-specific conditions with Maryland Dept. of the Environment (MDE) before relying on a deadline or inspection schedule.Official sources last reviewed: 2026-09-12

Regulation Overview

Permitting Authority

Maryland Dept. of the Environment (MDE)

Official Permit

General Permit for Construction (20-CP)

Inspection Frequency

Every 4 business days OR weekly + post-rain

Rain Event Trigger

0.25 inches or more in 24h
Check Missed Events

State vs. Federal (EPA)
Varies

Two Inspection Schedule Options

The weekly option carries an event-driven inspection requirement; the four-business-day option does not use that same post-rain cadence. Project and receiving-water conditions can add requirements.

Inspection Requirements for Maryland

Construction projects that disturb one or more acres—or smaller sites that are part of a larger common plan—commonly require stormwater permit coverage in Maryland. Eligibility, exemptions, local approvals, and project-specific conditions vary, so confirm coverage under the General Permit for Construction (20-CP) before construction begins.

Operational Insight

This schedule combines recurring and event-driven duties. Record rainfall or discharge events independently from the weekly calendar and document why each event did or did not trigger an inspection.

Specific State Nuance

The 20-CP permit allows inspections at least once every four business days, or once every seven calendar days plus within 24 hours after a storm producing 0.25 inch or more in 24 hours. MDE may require more frequent inspections for discharges to sensitive waters.

Common BMPs Checked in Maryland

Continue your field review

Check common controls in the BMP field guide, then compare them with your approved SWPPP.

Regulatory Filing

File Notice of Intent (NOI)

Agency Contact