California SWPPP Compliance

Quick Facts for California

  • Authority: State Water Resources Control Board (SWRCB) (CA)
  • Permit: Construction General Permit (2022 CGP)
  • Inspection Schedule: Weekly + pre-, during-, and post-QPE
  • Rain Trigger: QPE forecast: ≥50% chance and ≥0.5" in 24h
This page is a field reference, not legal advice. Confirm the current permit, local requirements, and project-specific conditions with State Water Resources Control Board (SWRCB) before relying on a deadline or inspection schedule.Official sources last reviewed: 2026-09-12

Regulation Overview

Permitting Authority

State Water Resources Control Board (SWRCB)

Official Permit

Construction General Permit (2022 CGP)

Inspection Frequency

Weekly + pre-, during-, and post-QPE

Rain Event Trigger

QPE forecast: ≥50% chance and ≥0.5" in 24h
Check Missed Events

State vs. Federal (EPA)
Varies

Forecast-Based QPE Inspections

California's QPE definition starts with both a probability-of-precipitation and quantitative-forecast threshold, then applies separate pre-, during-, and post-event inspection windows.

Inspection Requirements for California

Construction projects that disturb one or more acres—or smaller sites that are part of a larger common plan—commonly require stormwater permit coverage in California. Eligibility, exemptions, local approvals, and project-specific conditions vary, so confirm coverage under the Construction General Permit (2022 CGP) before construction begins.

Operational Insight

This schedule combines recurring and event-driven duties. Record rainfall or discharge events independently from the weekly calendar and document why each event did or did not trigger an inspection.

Specific State Nuance

All risk levels have weekly and qualifying precipitation event (QPE) visual inspections. The pre-QPE inspection is generally due within 72 hours before the event, during-QPE inspections every 24 hours, and a post-QPE inspection within 96 hours when actual accumulation reaches 0.5 inch or more. Confirm project-specific TMDL and monitoring requirements in SMARTS.

Common BMPs Checked in California

Continue your field review

Check common controls in the BMP field guide, then compare them with your approved SWPPP.

Regulatory Filing

File Notice of Intent (NOI)

Why Go Digital?

Handwritten logs are hard to read and easy to lose. Digital reports provide a timestamped, geo-tagged audit trail that protects your business.

"The best defense against an EPA audit is a perfect paper trail."